Brick chimney reinforcement
Construction plan
First, the brick chimney overview
Heating boiler room in a district of Guizhou
40m
High brick chimney
,
Built on
1987
year
,
Wall
100#(MU10)
Red brick
,50#(M5)
Mixed mortar masonry. Brick chimney design without considering seismic measures
,
Brick chimney wall and lining are
4
Festival and
2
Festival
,
Per degree
for
8m (
Overall lining height
13m),
Lining is refractory brick and refractory mud masonry
,
Wipe the soil cement mortar without the lining at the top
,
The barrel is not equipped with longitudinal reinforcement
,
Circumferential reinforcement
Φ
6@300.
1998
At the end of the year, a long-term covenant
5m
Vertical crack
(
Slightly inclined
),1
•
5m
The left and right cracks are more serious
,
Maximum slit width
3cm,
As shown
1
Shown.
Second, the analysis of the causes of cracks
On-site inspection
,
It was found that the oblique cracks basically appeared along the gray seam. According to the survey
,
Shenyang area
20
Nothing happened in the century
shock
,
even if
1975
Haicheng Earthquake
,
No cracks were found in the brick chimney.
,
Therefore, the possibility of earthquake action is first ruled out. On-site measurement with theodolite
,
The chimney is basically not tilted
,
And it does not meet the characteristics of cracks due to the inclination of the foundation.
,
Therefore, the factor of the base tilt is also excluded. Found when removing the top barrel
,
Part of the inner wall bauxite cement mortar falls off
,
Exposed red bricks. According to preliminary analysis
,
It is thought that it is due to the inner cylinder wall bauxite cement mortar falling off
,
Cracks caused by the temperature of the flue gas.
Third, the treatment measures
Since the brick chimney has been used
twenty two
year
,
Anti-seismic measures were not considered during design
,
And Party A asks for reinforcement treatment.
,
Brick chimney
To continue to use
15
About a year. On-site assessment by experts
,
The brick chimney reliability comprehensive rating
[1]
for
3
Subordinate
,
It is recommended to strengthen the seam while
,
Also for its overall seismic strengthening
,
Eliminate safety hazards and extend service life accordingly. The specific measures taken are as follows
:
1
• The holding layer of the brick chimney foundation is a clay boulder sand layer
,
After many years of settlement
,
Significant improvement in foundation bearing capacity
,
therefore
2
• will top
1
•
5m
The wall of the section with a wide crack is removed and rebuilt.
3
• on the top
1
•
5m
The following section of the crack is sprayed at the crack
M10
Cement mortar
,
Crack section
60
×
8
Steel plate spacing
1000mm
Hoop tight.
4
• Seismic reinforcement of brick chimneys using integral reinforced shotcrete.
5
• On top of the chimney
6m
The inner wall of the section brick is re-wiped
2cm
Thick heat-resistant cement mortar.
Fourth, the reinforcement check
This reinforcement check
,
They are all implemented in accordance with current structural design specifications. Calculation of vertical loads from old brick chimneys and new concrete cylinders
Shared
,
Horizontal load
(
Wind load, earthquake action, temperature action
)
All are taken up by new concrete cylinders. Old brick chimneys are not considered in the calculation to continue to withstand horizontal loads
,
To be safe
,
When calculating additional bending moments
,
It does not consider the restraining effect of the old brick chimney on the newly added concrete cylinder.
1
•known conditions
1 old brick chimney masonry material is
MU10
brick
, M5
Mixed mortar
,
Basic size
2
.
2 The basic intensity of the earthquake is
7
degree
,
Class II venue
,
Basic wind pressure
0
•
5kPa
.
3 new concrete tube wall thickness
80mm,
use
C20
Fine stone concrete injection molding.
2
• Heating temperature calculation
Flue gas temperature
T=400
°
C,
The outdoor outdoor maximum temperature is taken as
35
°
C,
The outdoor outdoor minimum temperature is taken as
-30
°
C,
According to the chimney
Design specification
[2] (GBJ51-83),
Calculated the maximum heating temperature of the inner wall of the concrete cylinder
Tmax=130
°
C,
Maximum heat temperature of the outer wall
Tmax=75
°
C,
Are less than the specified limits
Tmax=200
°
C,
To simplify calculations
,
Take the average temperature of the concrete wall
Tc=100
°
C,
Average steel bar temperature
Ts=100
°
C
. See the specifications for the material properties of concrete and steel bars under temperature.
3
• Internal force calculation
According to the Code for Seismic Design of Buildings
[3] (GBJ11-89),
Brick chimney
(H
≤
60m)
The basic natural vibration period can be calculated as follows
:
T1=0
•
26+0
•
0024*H2/d2(1)
H
- the height of the chimney from the top of the foundation
(m)d
—The outer diameter of the cross section of the chimney
(m),
For this project
Concrete wall thickness should be considered
T1
- the basic natural vibration period of the chimney
(S),
The project is calculated
T1
Got
T1=0
•
26+0
•
0024*332/2
•
832=0
•
586(s)
According to the Code for Loads of Building Structures
[4] (GBJ7-89),
Building Seismic Design Code
(GBJ11-89),
Chimney Design Code
(GBJ51-83),
Carry out calculations of dead load, wind load and earthquake
,
Consider the base tilt and sunshine effects when calculating additional bending moments
(
take
Tan
θ
=0
•
06,
Δ
T=20
°
C),
The calculated internal forces of each section are shown in the table.
2~
table
3
.
Section number elevation
(m)
Dead load
NK(kN)
Wind load earthquake
4
• Section reinforcement calculation
Under the limit of carrying capacity
,
Structural importance coefficient γ of newly added concrete cylinder
0
take
1
•
1,
Body seismic capacity adjustment system
Number γ
RE
take
0
•
85,
consider
2
The combination of loads is used to check the section strength.
1
•
4*
Wind load
According to the Chimney Design Code
,
Carrying capacity calculation for each horizontal section
,
Longitudinal area combination I
As=3400mm2,
group
Combined II
As= 4100mm2,
Solid length
40
Φ
12, As = 4524mm2,
Circumferential reinforcement
Φ
8@250.
5
• Use phase check
Consider the following stages in the use phase
3
The combination is used to check the stress and crack width of each section.
Combination I
:
Dead load
+
Wind load
Combination II
:
Dead load
+
Wind load
+
Temperature effect
Combination III
:
Dead load
+
Temperature effect
Calculated
:
Concrete compressive stress σ
Cmax=2
•
4MPa,
Reinforcement stress σ
s=50MPa,
Horizontal crack width
Wmax=0
•
13mm,
Vertical crack width
Wmax=0
•
11mm,
Both meet the normal use limit state requirements.
V. Reinforcement construction steps and construction measures
1
• Will the top of the chim
1
•
5m
The old brick chimney wall with a wide crack is removed.
2
• Will the top of the chim
1
•
5m
The following section crack injection
M10
Cement mortar
,
Make the crack closed.
3
•use
60
×
8
Steel plate
,
spacing
1000mm
Clamping crack section
,
And beyond the crack section
1000mm,
To prevent cracks from continuing to expand.
4
• will top
1
•
5m
Section reuse
MU10
brick
, M5
mix
Masonry masonry to the top ring beam
,
Circumferential reinforcement when laying
Φ
8@250,Vertical reinforcement
Φ
12@300,And anchored into the top ring beam
250mm
.
5
• Chisel the surface of the old brick chimney
,
Eliminate crusty parts and dirt
,
Rinse with water
,
And brush together with cement slurry
,
To make a new mix
The concrete cylinder is firmly bonded to the old brick chimney.
6
• Add a base ring beam to the top of the old brick chimney foundation
240
×
300,
Reinforcement
6
Φ
12/8Φ
@200.
7
• Ligation of longitudinal and circumferential reinforcement
,
Longitudinal reinforcement should be anchored into the newly added foundation ring beam and the rebuilt masonry top ring beam
,
The new concrete cylinder and the old brick chimney are integrated from the foundation to the whole.
8
•along
chimney
Whole body sprayC20
Fine stone concrete
80mm
thick
,
Pouring top ring beam
360
×
240,
Reinforcement
6
Φ
12/Φ
8@200.
9
• will top
6m
Loose bauxite cement mortar removal in the inner wall of the brick
,
Re-wipe
2cm
Thick heat-resistant cement mortar.
KNB1-32 Miniature Circuit Breaker
KNB1-32 Mini Circuit breakers, also named as the air switch which have a short for arc extinguishing device. It is a switch role, and also is a automatic protection of low-voltage electrical distribution. Its role is equivalent to the combination of switch. Fuse. Thermal Relay and other electrical components. It mainly used for short circuit and overload protection. Generally, According to the poles, mini Circuit breaker can be divided into 1P , 1P+N , 2P, 3P and 4P.
KNB1-32 Miniature Circuit Breaker,KNB1-32 Electronics Miniature Circuits Breaker,KNB1-32 Automatic Miniature Circuit Breaker,KNB1-32 Mini Circuit Breaker
Wenzhou Korlen Electric Appliances Co., Ltd. , https://www.zjmannualmotorstarter.com